Job costing: forecast the cost to complete a remodel
Use actual cost plus remaining cost to spot a budget overrun before the job ends.
Choose a consistent reporting date
Record actual job costs through a stated date. Include costs consistently and avoid counting a bill in both actual costs and expected remaining costs. Track commitments not yet recognized as actual costs in the remaining forecast when relevant.
Estimate the remaining work
Review unfinished labor hours, material orders, subcontractor balances and known changes. For a job with an approved $10,000 selling price and $7,500 cost budget, suppose actual costs are $5,200 and remaining costs are $2,900. The projected completion cost is $8,100.
Compare against the revised budget
Projected cost is $600 above the $7,500 budget. Projected gross job profit is $1,900, or 19% of approved revenue, assuming the chosen cost definition is consistent. Do not confuse actual cost to date with final cost or projected gross job profit with company net income.
Act before the next commitment
Identify the drivers of the $600 variance, such as extra labor or material waste. Update the remaining cost estimate with new information. Record approved changes separately and do not assume a customer will pay for unapproved scope. Review the forecast regularly, not just when the project closes.